In the described critical path scenario involving scaffold erection and plaster repairs, what should the CM recommend for a scheduled time extension and compensation?

Prepare for the CMAA Certified Associate Construction Manager Test. Study using comprehensive materials including flashcards and multiple-choice questions. Each question is accompanied by hints and explanations. Ensure success on your exam!

Multiple Choice

In the described critical path scenario involving scaffold erection and plaster repairs, what should the CM recommend for a scheduled time extension and compensation?

Explanation:
When the schedule is driven by the critical path, delays on those key activities push the entire project finish date. If scaffold erection and plaster repairs extend the critical path, the construction manager should seek an Extension of Time for the actual delay and also obtain compensation for the additional General Conditions costs that arise from that extended period. This pairing protects the project timeline and fairly covers the overhead and site overhead costs tied to the longer duration. In this scenario, five days of additional time addresses the measurable delay on the critical path caused by those tasks, while four days of added General Conditions costs reimburse the extra overhead, supervision, temporary facilities, and other site-support expenses incurred during the extended period. The other options don’t adequately pair time extension with the corresponding GC costs or they misstate the extent of the delay, which is why they’re less appropriate.

When the schedule is driven by the critical path, delays on those key activities push the entire project finish date. If scaffold erection and plaster repairs extend the critical path, the construction manager should seek an Extension of Time for the actual delay and also obtain compensation for the additional General Conditions costs that arise from that extended period. This pairing protects the project timeline and fairly covers the overhead and site overhead costs tied to the longer duration.

In this scenario, five days of additional time addresses the measurable delay on the critical path caused by those tasks, while four days of added General Conditions costs reimburse the extra overhead, supervision, temporary facilities, and other site-support expenses incurred during the extended period. The other options don’t adequately pair time extension with the corresponding GC costs or they misstate the extent of the delay, which is why they’re less appropriate.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy