An effective cost management plan includes which phases' costs?

Prepare for the CMAA Certified Associate Construction Manager Test. Study using comprehensive materials including flashcards and multiple-choice questions. Each question is accompanied by hints and explanations. Ensure success on your exam!

Multiple Choice

An effective cost management plan includes which phases' costs?

Explanation:
Costs occur in every phase of a project, so a robust cost management plan must cover all phases—from design through procurement, construction, and post-construction. Early-phase costs affect feasibility and value, construction costs drive the majority of the budget, and post-construction costs influence the total life-cycle cost through operations, maintenance, and warranties. Leaving out any phase risks underestimating total cost and losing budget control, so the plan should address costs across design, procurement, construction, and post-construction.

Costs occur in every phase of a project, so a robust cost management plan must cover all phases—from design through procurement, construction, and post-construction. Early-phase costs affect feasibility and value, construction costs drive the majority of the budget, and post-construction costs influence the total life-cycle cost through operations, maintenance, and warranties. Leaving out any phase risks underestimating total cost and losing budget control, so the plan should address costs across design, procurement, construction, and post-construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy